Three-Phase Transformers: Principles, Types, and Applications

A three-phase transformer changes voltage between two three-phase systems using magnetically coupled windings on a shared core, or as a bank of three single-phase units. How the primary and secondary windings are connected (wye or delta) sets the available voltages, grounding and harmonic behavior.

Last reviewed · Published by Essential Systems

NABCABCWYE (STAR)DELTA

Construction

  • Three-legged core: one core with a winding set on each leg. Compact and the most common design.
  • Bank of three single-phase units: easier to replace one failed unit; used in some utility and large industrial installations.
  • Dry-type: air-cooled, typical indoors in commercial buildings at low voltage.
  • Liquid-filled: oil or less-flammable fluid. Typical for pad-mounted utility and larger units, with higher overload tolerance.

Winding configurations

ConnectionTypical useNotes
Δ–Y (delta–wye)Building service and step-down, e.g., 480Δ to 208Y/120Grounded neutral on secondary; 30° shift
Y–ΔStep-down at generating stations; some industrialNo secondary neutral
Y–YSome utility distributionNeeds careful grounding; tertiary winding sometimes added
Δ–ΔOlder industrial systemsCan run open-delta at 57.7% capacity if one unit fails

Deeper comparison: Wye vs. Delta Connections.

Sizing by kVA

kVA = √3 × V × I ÷ 1,000. A 75 kVA transformer at 208 V delivers about 208 A full-load secondary current. Size for calculated demand plus growth, and consider non-linear loads, which may call for a K-rated or harmonic-mitigating transformer. The Power Calculator handles the arithmetic.

Standard three-phase kVA ratings (selected)
kVAFull-load A @ 208 VFull-load A @ 480 V
308336
4512554
7520890
112.5312135
150416180
225625271
300833361
5001,388601

Impedance and fault current

Percent impedance (%Z) limits the fault current a transformer can deliver. A rough upper bound is full-load amps ÷ (%Z ÷ 100), so a lower %Z means higher available fault current downstream. That affects the interrupting ratings of panels and breakers. NEC 110.24 requires available fault current to be marked at many service locations.

Installation considerations

  • Overcurrent protection on primary and secondary per NEC 450.3
  • Grounding and bonding of the secondary as a separately derived system per NEC 250.30
  • Ventilation, clearances and sound levels for dry-type units
  • DOE efficiency requirements for distribution transformers